Estimate to Commitment
Episode 5: Estimate to Commitment
How a job gets bought out
How general contractors go from carry number to signed subcontract, and how specialty contractors turn an estimate into material purchases. Bid leveling, scope, and qualification without the human bias, plus pending POs built straight from the estimate.
Buyout · 16 min
Opens
This episode opens November 17 at 9 AM ET.
Get free access to series updates
By signing up you agree to get emails about this series. Unsubscribe anytime.
Read the transcript
What about estimate to commitment? I mean, let's talk about Yeah. Before and after. Let's do estimate to commitment.
You know, it's I'm going to talk out of both sides of my mouth, I guess. One is the subcontractor's world and one is the GC's world.
Yeah. And I'm going to talk about buyout for a general contractor which has gotten better with the advent of things like BuildingConnected TradeTapp you know SmartBid there's some cool bidding tools out there and it has made them more efficient the buyout moment. So for those that are you know watching this more for technology than construction I'm going to quickly explain how it works today. Today, when you're a general contractor and you don't do most of your work, your responsibility is to find subcontractors that can't.
There's two reasons you do that. One is risk transference, right? I don't want to do the mechanical. I want to transfer the risk to the mechanical contractor. Second is expertise. You don't have the expertise in house. So, you need to find somebody that is an expert, right? Your goal is to find the lowest price with the highest expertise. That's the goal. That's the job. So when you go to an estimate, you get a carry number and you ask as many people on the street as possible, can I get a price on these bid on these drawings and these specs.
Subcontractors are just like everyone. The specs and the drawings are weak. So they guess because everybody's guessing. It's all educated guesses and they hopefully somebody guesses right. And you carry a number. And what carry number means that's a number I'm going to represent to my client that I think I can do the mechanical for instance or concrete. Then the PM gets involved. So the estimator carries the number. Then the project manager is involved and they're going to actually buy it out. That's what we call estimate to commitment.
They're going to go and find the subcontractor. Oh, I don't like this one. I'm going to go with that one. I have a better relationship. You nudge wink that you know depending on the part of the country you're in. Maybe somebody dropped an envelope on a desk where whatever the situation is, the real subcontractor is selected not to exceed the carry number unless there's a major scope change and then they sign a legally binding agreement with the subcontractor. Where the industry has focused most of their efforts is on getting carry numbers, which means a big list of subcontractors that can send bids to you.
That's why every subcontractor is inundated with ITBs with invitations to bid.
So that's what's helped. There's a rolodex in BuildingConnected. You find a contractor. Wow, that's cool. You send it an email. The email has bids and, you know, drawings and specs and the bid. You get a price back. Hopefully, you get coverage. They tell you what they're going to bid on and you're done. Now, let's talk about the real cost of that. What could go wrong? Right? I'm sending a 100,000 emails to 100,000 strangers. And of course, I already know who I'm buying from, but whatever.
I'll carry a number. I'm just trying to keep this other guy honest. So, what does that produce? That produces the highest level of human bias in the entire construction industry. And human bias, unfortunately, is generally wrong. So, estimators are doing educated guesses. Project managers are selecting contractors on ego and relationships. Big problem because we're not necessarily reducing risk and increasing expertise. We're choosing Chuck because we have dinners on Friday. So this is a major issue. That's where AI changes the game. So we've now crossed the precipice where a list of 600,000 general contractor or sorry specialty contractors to a GC that's not hard to create.
You can create that overnight. That's not hard. Google maps integration AI knows about Google Maps. AI knows about LinkedIn. AI can find the contractors you're looking for. AI knows who works there currently and AI knows their mobile number and their email. So that's all that whole infrastructure of like a system that just is a rolodex. That's over. AI can do that. I mean Briq alone has 2.3 million companies in America that does specialties, you know, stuff whether it's a guy in a truck all the way to the largest contractors in the world.
So that's done. So you know find you want coverage done Otto just like a BuildingConnected does mass emailing it looks more personalized because it is personalized but again boom invitations a bit that whole thing AI will handle cradle grave cradle grave where things get interesting is on pre-qualification so when or qualification so when you carry a number you don't care if they're qualified or not generally but when you sign a legally binding contract with them you scope of work other than just saying bid the plans and specs and that's your scope of work which is which is what we do today.
Sometimes you really got to know what was in the bid. You don't have time to know what was in the bid. Chuck bought you dinner. It's his. So the idea here is it's the buyout process needs to be orchestrated across those steps I talked about. M the orchestration is extremely complex because it involves people that don't work at your company.
Every bid needs to be read in detail. Exclusions, exclusions, and alternates. Bid leveling needs to be done not by a human that has bias, but by a machine. And Otto does that really, really well. You're still in control as a contractor. You still choose your, you know, Otto is not your autonomous leader. It's going to tell you what's what, but you still choose who you're going to go with, but then you go in eyes wide open. And it really makes for those CEOs that are listening to this, it really makes Chuck's dinner buying a little less easy to push through.
A lot less easy. And if you're a GC CEO, you know, a lot of your PMs go to be PMs and executives at subcontractors. You ever wonder why that is? So take the human bias out of the buyout. Make sure the risk is reduced by having the AI write the contract, the scope of work. Have the ultimate qualification of the contractor, their financials, their past history, not only the form they fill out, but the corpus we discover on them. Just like your own corpus, that own book of the dead of that company.
Understand where they're going, how they went there, and what their growth patterns were. Let the machine do that. All you have to do is press the button on who you want to select. And if you went back, and not to hark on these older systems, if you go back to these older systems, these buyout systems or these project management systems, I want you to imagine how much of what I just said was really, really important in reducing risk on your project was actually done in those systems.
Almost nothing. You go in there and you type the bid in a lump sum fashion, maybe a little bit of detail, possibly. You go in and I'm going to buy from Chuck anyway. And you press the button and what do you really do? You do a little bit of accounting cost coding. You don't even have their schedule of values in there. They're going to bill you down the road. We're going to talk about that. Their schedule values is going to be not in there.
We don't build projects based on cost codes. Concrete is an 03300 one line 03300s a million dollars. That's how we're accounting for it because we don't want to type data into these PM or accounting systems and construction companies lose money. That's the idea is not a sub agent that makes it easier to put in 03300s and a dollar amount. You don't need a bot just doing that, which is what we used to do. No, you need a bot managing the process, orchestrating it.
You need the bot to understand that every project is a snowflake. That it needs to understand that snowflake. It needs to be generative during that process. That process needs to be flexible enough to really rebuild itself during the bid process. That entire thing needs to be autonomous. I don't have enough people to bid the work I got. M it has to 80% of that has to be run by the machine and you know when it raises a hand I'd rather not be a red cell in an Excel spreadsheet that everybody's squinting to see on bid day.
I'd rather say hey there's a problem here in plain English. That's what changes when you go from estimate to budget or estimate to commitment for a general contractor. The work is done for you in plain English. Now, it's a lot different in the subs. So, I'm going to talk about estimate to purchase order material. We're going to talk about labor later, but for anybody watching this that's a subcontractor, you know, the reality is, you know, the GC's really have transferred a lot of risk to you.
So, let's say you're a mechanical sub and you did an educated guess. You guessed on how much things would cost. It's a little bit more of precise science because you're measuring and you're saying, "Oh, if these are the drawings, this is how much wire I need, whatever." And wire costs a dollar a foot and I need a hundred. So, it's 100 bucks and it takes an hour to put it in. So, it's one person for one hour and 100 bucks. That's their estimate.
Now, when that becomes the budget, that richness of what the work plan is disappears because you're taking an estimate that's in very granular detail as a sub and trying to shove it into a little tiny box that exists on a 45year-old accounting system or a PM system that was not built for you. And you know, it's not built for you no matter what the marketing says. When we built and I built two of the top PM systems on the market today, we focused only on GC's.
And then when we ran out of GC's, we're like, "Oh, we're subs." So that was the idea, right? If you don't have that richness, I'm going to tell you, your profit is disappearing already. And the idea here is those that hund you remember I mumbled through 100 feet, dollar a foot, 100 bucks. One day Chuck or Jenny is going to go and buy a 100 feet, but they're probably going to buy 200 feet or 50. And they're not going to buy it for a buck.
They're going to buy it for two. And you know how that process works today? It's almost embarrassing. Chuck Jenny goes to the supplier, picks up the phone, walks into the room. I need a 100. Okay. You got a PO number? Give me a sec. Francis, what's the PO number? What's my next PO number? 30. Okay. PO number 30. I need 100. Okay. And we're not going to talk about it again until that vendor calls and asks for the money. And they're going to have an invoice and they're going to take that invoice and it's going to say PO30.
And I'm going to look at PO30 and it says Ferguson 30 and then nothing on it. Shell and then and then everybody yells at AP. You know the reality is that estimate should be producing pending purchase orders that get don't get created in the field but get executed when you actually buy the material. And you would be doing that if you had the time to do it. You would have these pending POS, right? You'd have them in detail by material based on the estimate.
Well, the estimator is doing something in Excel. You're not using Excel. The estimate is long gone. It's in some C drive, O drive. You know, who knows where it is probably. Then the accountant took the estimate and shoved it into a cost code, which none of us work against. We don't, you know, electrical subcontracting isn't one cost code 16. It's real. It has schedules. It has activities. It has crews. It as people. All that richness is dead on that budget. And you know what else is dead?
Your profit. Because you're going to go out and buy too much, spend too little, buy the wrong thing, send it back, have damage, all because the estimate is on an island because you don't have the time to turn it into a commitment or a pending commitment. So, as a subcontractor, when you think about how much money can leak out of your company in materials, you have to think how does AI sit on top of that estimate comes in. AI doesn't stop. It's going to read the whole estimate.
It's going to create a material list. It's going to track alternates. It has access to the web. It's going to look at what's being recalled, what's overpriced, what vendor went out of business, what vendor has it on sale potentially. It's going to look up cataloges. Is going to log in to any catalog that you give it access to. It's going to try to find the best fit vendor. You obviously are in charge, but it's going to create a headless PO with the items on it that you're supposed to buy and when you're supposed to buy it because it's on the schedule.
You would have do this if you had the time. AI doesn't invent work. AI just does the work. And then when the accountant Francis has to give a PO number, you never have to talk to Francis. You talk to Otto. Otto, what's my PO number for the wire on this project? Otto says, "What wire?" If there's no estimate or says, "Oh, the wire that you need for the next work package. This is the number." The invoice comes in, Otto has access to the buyer's email.
The order acknowledgement has already been processed because every vendor likes getting paid. So, the order acknowledgements are being sent. Maybe we've taken a picture of a packing slip and AP doesn't become a job, it becomes an approval. So that's that's the key differences. It I'm very passionate about estimate commitment specifically around the fact that the reason why there's like some negativity around construction is we are we are really mean to each other and like GCs are mean to subs owners are mean to GCs.
It's and material suppliers are mean to vice versa in the subcontract layer. It's like a it can be a very negative industry in that regard because everybody's yelling at each other. But it's it's like, you know, it's blind, you know, you're blind of it. You have partial hearing and your tongue's being cut out and that's why everybody's just bashing each other. The idea here is that, you know, sunlight is the best disinfectant and I think that's what AI provides. We hope that this series was genuinely helpful.
If it sparked new ideas, if it gave you an inspiration to pursue new AI projects in the business, reach out to us. We're here to help. So we thank you for your time and we thank you for watching.